This bid is for exhaust fan installation and associated gas piping and electrical updates at Columbia Pool, 600 Columbia St, Turlock, CA 95380.
This bid has closed.
Buyers often post the same work again. Set an alert below and we will email you when a similar California bid is posted.
What the job is
Exhaust fans: Furnish and install two Plastec P20ST4P033 polypropylene blowers, each rated 500 CFM at 0.50-inch static pressure with a 1/3 HP motor, factory support stand, disconnect, and D15011 VFD (115V single-phase input, 208V three-phase output).
Ductwork: Install 10-inch stainless-steel ducts, stainless-steel grilles and transitions, supports, service access panels, roof flashing, and 45-degree exterior terminations with 1/2-inch stainless-steel mesh. Include startup and air balancing.
Gas piping: Remove and reconfigure boiler supply piping using 2-inch and 1-1/2-inch Schedule 40 black steel, including fittings, valves, unions, supports, exterior coating, and pressure and leak testing.
Electrical: Include breakers, branch wiring, conduit, grounding, wall switches, timer, and VFD and equipment connections.
Scheduling: Complete within 30 working days, with substantial completion within 25. Gas interruptions must occur on a Friday, with boiler service restored by 3:00 p.m.; include Knorr Systems’ authorized representative for shutdown and startup.
Site visit: Mandatory walkthrough on October 9, 2026, at 9:00 a.m. at the pool.