This bid is for water main replacement engineering services at six locations in Salt Lake City, Millcreek City, and Holladay City, Utah.
This bid has closed.
Buyers often post the same work again. Set an alert below and we will email you when a similar Utah bid is posted.
What the job is
Locations and quantities: Approximately 23,900 linear feet total: 1140 East, 4270 South–4380 South, Millcreek (1,600 LF); Heughs Canyon neighborhood, Holladay (6,000 LF); Olympus Hills neighborhood, Holladay (5,800 LF); Parkview Drive, Park Terrace Drive–3892 South, Millcreek (5,300 LF); Cheyenne Street, 500 South–600 South, Salt Lake City (700 LF); and 11th Avenue, L Street–Virginia Street, Salt Lake City (4,500 LF). Existing mains range from 6–12 inches.
Pre-design: Survey and mapping, utility investigation with test holes, soil corrosivity review, hydraulic modeling for capacity, demand and fire flow, and construction phasing. Include seismic/structural analysis and trenchless replacement alternatives for 11th Avenue.
Design: Horizontal and vertical design, corrosion control, permitting, 60%/90% reviews, cost estimates, and final plans and specifications stamped by Utah-licensed engineers.
Support: Bidding assistance, construction submittal and RFI reviews, change orders, commissioning, as-built drawings, closeout, and public engagement through design and construction.
Schedule: Pre-design completion in February 2027; design completion and Phase 1 bid package ready in March 2027.