A government solicitation can run 40 pages or 400. You don't have to read every page with the same care. A few blocks on the cover page and three lettered sections answer most of what a small vendor needs to know: can I bid, what is the work, how do I submit, and how will they pick the winner.

This is Chapter 4 of our How to Win Government Contracts series. It covers federal solicitations under the Federal Acquisition Regulation (FAR). State and local bids are built differently, but they ask most of the same questions.

Note: The FAR is being rewritten under the FAR Overhaul, and some agencies already use the new text under class deviations. The part and clause numbers in a solicitation may not match the ones below. When they differ, follow the solicitation.

RFQ vs RFP vs IFB vs Sources Sought: what each one asks for

The type of document tells you what kind of response is expected and how the award is decided.

  • RFQ (Request for Quotation), FAR Part 13. Used for simplified acquisitions. You send a quote, usually short. A quote is not a binding offer until the government issues an order and you accept it. See our FAR Part 13 glossary entry.
  • IFB (Invitation for Bids), FAR Part 14. Sealed bidding. Bids are opened at a set time, and award goes to the responsible bidder whose bid meets the terms and is lowest in price (counting price-related factors). There are no discussions.
  • RFP (Request for Proposals), FAR Part 15. Contracting by negotiation. Proposals are scored on the factors in Section M. That might be lowest price technically acceptable, or a best-value tradeoff between price and quality.
  • Sources Sought / RFI. Market research, not a solicitation (see FAR 15.201(e)). Nothing is awarded from it. Your answer helps the agency decide whether to set the real buy aside for small businesses.
What each notice type asks forSources Sought / RFIMarket research. No award.RFQ · FAR Part 13Send a price quote.IFB · FAR Part 14Sealed bid. Lowest responsive price.RFP · FAR Part 15Proposal scored on Section M.
Four notice types you will see on SAM.gov, and what each one asks you to send.

The SF 1449 and SF 33 cover pages, block by block

Most federal solicitations start with one of two standard forms. The cover page is the fastest way to tell whether a bid is worth your time.

SF 1449 (commercial products and services)

This form is used for commercial buys under FAR Part 12, including many RFQs. The blocks to check first:

  • Block 5: Solicitation number. Use it in every email and file name.
  • Block 8: Offer due date and local time. Check which time zone "local" means.
  • Block 10: Whether the buy is unrestricted or set aside (small business, WOSB, EDWOSB, HUBZone, SDVOSB, 8(a)), plus the NAICS code and size standard.
  • Block 14: Method of solicitation: RFQ, IFB or RFP.
  • Blocks 19-24: The schedule of items, with quantity, unit, unit price and amount. This is where your price goes.

SF 33 (sealed bid and negotiated)

The SF 33 is used for IFBs and RFPs that follow the uniform contract format. It shows the type of solicitation (sealed bid or negotiated), where and when offers are due, a contact for questions, and a table of contents for Sections A-M. It also has a block where you list the amendments you are acknowledging, and the offeror's signature block.

Uniform contract format: Sections A-M and what matters to a small vendor

IFBs and RFPs usually follow the uniform contract format in FAR 15.204-1 (and FAR 14.201-1 for sealed bids). Commercial buys on the SF 1449 use a shorter format, but the same information is in there.

Sections A to M in four parts, with C, L and M highlightedPart I · The Schedule (A-H)B prices, F delivery, E inspectionC: scope of workPart II · I: contract clausesPart III · J: attachmentsPart IV · K reps and certsL: instructionsM: evaluation
The uniform contract format (FAR 15.204-1). Sections C, L and M are the three a small vendor reads most closely.
  • Section C (scope of work): What you must actually do, where, how often and to what standard. Price from this, not from the title.
  • Section L (instructions): Page limits, file formats, volumes, how and where to submit. Offers that ignore Section L can be rejected before anyone reads them.
  • Section M (evaluation): How they pick the winner. Lowest price technically acceptable means a clean, compliant low price wins. A tradeoff means past performance and your technical approach count too.
  • Also check: B (the price schedule), F (period and place of performance), I (clauses such as the limitations on subcontracting) and J (attachments, often including the wage determination).

Set-aside, NAICS code and size standard: can you bid?

The contracting officer assigns one NAICS code to each solicitation (FAR 19.102). That code's SBA size standard decides who counts as small for this buy. Your company's size is measured against that code, not against the codes you picked in SAM.gov.

If it is set aside for small business, you must be small under that standard, and registered in SAM.gov with your representations up to date. If it is set aside for 8(a), HUBZone, WOSB or SDVOSB, you also need that status. If it is unrestricted, anyone can bid.

Deadlines, Q&A period, amendments and how to acknowledge them

Every solicitation sets its own dates. Put each one on your calendar the day you download it.

Solicitation timeline from posting to due dateSolicitation postedDownload everything, note datesQuestions dueBy the deadline in Section LAmendments postedAnswers, changes; acknowledge eachOffers dueStated date and local time
The usual order of events. The actual dates are always in the solicitation and its amendments.
  • Questions: Section L, or the instructions in an RFQ, gives a deadline and an email address for questions. Questions sent late may not be answered.
  • Amendments: Answers and changes come out as amendments, usually on the SF 30, posted to the same SAM.gov notice. Turn on notifications or check back often. Amendments can change the due date, the scope or the wage rates.
  • Acknowledge every one: Sign the SF 30, list the amendment numbers on the SF 33 or SF 1449, or follow whatever method the notice gives. Under sealed bidding, a bid that does not acknowledge a material amendment can be found nonresponsive (FAR 14.405).
  • Late is late: Offers received after the stated time are generally not considered (for example FAR 52.212-1(f)). Submit early.

Wage determinations, bonding, insurance and site visits

These four items change your price the most, and they are easy to miss in the attachments.

  • Wage determinations: Service contracts over $2,500 are covered by the Service Contract Labor Standards (FAR 22.10). Construction over $2,000 is covered by Davis-Bacon (FAR 22.4). The attached wage determination sets the minimum wage and fringe rates per job title. Wage determinations are also published on SAM.gov.
  • Bonds: Federal construction contracts over $150,000 require performance and payment bonds (FAR 28.102-1). When those bonds are required, a bid guarantee is usually required too (FAR 28.101-2). Check with your surety before you price.
  • Insurance: Look for the insurance clause and its minimum amounts, often in Section I or H (see FAR 28.307-2).
  • Site visits: If a site visit is offered (FAR 52.237-1), go if you can. Registration usually closes ahead of time. You are expected to know the site conditions either way.

A 10-minute bid/no-bid read: the 8 lines to check first

Before you spend hours on a bid, check these eight lines. If any of them is a "no", move on.

  1. Type: RFQ, IFB or RFP? Do you have time for what it asks?
  2. Due date and time zone: Can you submit at least a day early?
  3. Set-aside: Are you eligible?
  4. NAICS and size standard: Are you small under this code?
  5. Place of performance: Can your crew reach it at a price that works?
  6. Scope in Section C: Is this work you already do?
  7. Evaluation in Section M: Lowest price, or a tradeoff that asks for past performance?
  8. Wage rates, bonds and insurance: Can you meet them and still make money?

For where to find bids in the first place, see how to find small federal contracts to bid on. For the full roadmap, see how to get government contracts.

Do the work without writing the proposal: subcontract to XL Eagle at your price

If the scope fits your trade but Sections K, L and M look like too much paperwork, there is another route. XL Eagle LLC (UEI K6SYWSWZAMY9, CAGE 11R42) finds open federal, state and local bids and bids as the prime contractor. You send us your price. If we win, you do the work as our subcontractor at your price.

There are no fees to bid, and we send nothing to the buyer without your OK. See how it works, and use our subcontractor quote template to send a clean price.

Find open bids in your trade

Search open federal, state and local bids free, with no login. XL Eagle bids as the prime and you subcontract at your price. No fees to bid.

Find open bids in your trade →

Browse by location or trade: open contracts in Texas or all states and trades.

Frequently asked questions

What is the difference between an RFQ, an IFB and an RFP?

An RFQ (request for quotation) is used for simplified acquisitions under FAR Part 13 and asks for a price quote. An IFB (invitation for bids) is used for sealed bidding under FAR Part 14 and is usually awarded to the lowest responsive, responsible bidder. An RFP (request for proposals) is used for negotiated contracts under FAR Part 15 and is evaluated on the factors listed in Section M.

Which sections of a solicitation should I read first?

Start with the cover page (SF 1449 or SF 33) for the due date, set-aside and NAICS code. Then read Section C for the scope of work, Section L for how to submit, and Section M for how offers are scored. Check the attachments for wage determinations and any amendments.

Do I have to acknowledge every amendment?

Yes. Acknowledge each amendment the way the solicitation says, for example by signing the SF 30 or by listing the amendment numbers on the cover page. Under sealed bidding, failing to acknowledge a material amendment can make a bid nonresponsive.

Can I bid on a sources sought notice?

No. A sources sought notice is market research, not a solicitation, and nothing is awarded from it. Responding is still worth it because the answers help the agency decide whether to set the future buy aside for small businesses.

Can I do government work without writing a proposal?

Yes, as a subcontractor. With XL Eagle, you send your price for an open job, XL Eagle bids as the prime contractor, and if it wins, you do the work as XL Eagle's subcontractor at your price. There are no fees to bid.

This guide is general information, not legal advice. Official sources: https://www.acquisition.gov/far/part-13, https://www.acquisition.gov/far/part-14, https://www.acquisition.gov/far/part-15, https://sam.gov

Plain-English answers to common government contracting questions: SAM.gov registration, finding small federal contracts, DLA DIBBS.

Have a price for a government job?

Send it to us. XL Eagle writes and submits the bid under our registrations, free to you. If we win, you do the work at your price.

Find a job and send your price →