This bid is to replace two boilers at the Itawamba Community College Student Services Building, Fulton Campus, Fulton, Mississippi 38843.
Due
November 19, 2026
5 days left
Location
Fulton, MS
Mississippi
Posted on
ms.gov
Notice ID
3170036938
Please quote replacing two boilers with two Weil-McLain SVF 1000 natural gas condensing boilers at the Student Services Building, Itawamba Community College, Fulton Campus, Fulton, Mississippi 38843.
Equipment: Two Weil-McLain SVF 1000 natural gas condensing boilers, each 1,000,000 BTU/hr input, 965,000 BTU/hr output, 96.5% efficiency, 10:1 turndown.
Installation: Remove existing boilers and install hydronic and gas piping, insulation, venting, combustion air intake, condensate drainage and neutralization, controls, and electrical connections at 120V, single-phase, 60Hz.
Phasing: Put one new boiler into operation before removing the remaining old boiler; the building stays occupied.
Startup: Factory-authorized startup, certified testing and balancing, and operator training.
Schedule: Substantial completion within 60 calendar days after authorization to begin.
Warranty: One year on materials and workmanship; ten years on boiler heat exchangers, including thermal shock coverage.
Please confirm availability and send your quote by November 19, 2026.
The original documents
Deadline: November 19, 2026
See the original on www.ms.gov
Bidding it yourself? Get the full package and submit on ms.gov before November 19, 2026.
What they need
EquipmentTwo Weil-McLain SVF 1000 natural gas condensing boilers, each rated at 1,000,000 BTU/hr input, 965,000 BTU/hr output, 96.5% efficiency, and 10:1 turndown.
InstallationInclude existing boiler removal, hydronic and gas piping, insulation, venting, combustion air intake, condensate drainage and neutralization, controls, and electrical connections at 120V, single-phase, 60Hz.
PhasingPut one replacement boiler into operation before removing the remaining existing boiler. The building will remain occupied.
StartupInclude factory-authorized startup, certified testing and balancing, and operator training.
ScheduleSubstantial completion within 60 calendar days after authorization to begin.
WarrantyOne year on materials and workmanship; ten years on boiler heat exchangers, including thermal shock coverage.
Past history: who won Electrical work in Mississippi
Recent federal contract awards (federal buyers) in the same industry in Mississippi, from USAspending.gov. These are comparable jobs, not earlier rounds of this exact solicitation.
Typical award:$21K to $90Kmiddle half of 14 recent awards · median $65K