Hayes Building, 601 North Central Avenue, Baltimore, MD 21202; Paul Laurence Dunbar Middle School, 540 North Caroline Street, Baltimore, MD 21205; Benjamin Franklin Building, 1201 Cambria Street, Baltimore, MD 21225; Paul Laurence Dunbar High School, 1400 Orleans Street, Baltimore, MD 21231; and Dig
Can you do this job? Tell us your price.
We write the bid, handle the paperwork, and submit it for you. No upfront fees.
Got it.
You send a priceOne number, before November 16, 2026.
We bid itXL Eagle submits the bid as the main contractor.
You do the workIf it is awarded, you do the job as our subcontractor.
Scope: Replace designated doors and hardware and modify existing frames as needed, per drawings and door schedules. Include labor, materials, equipment, finishing, and disposal.
Security hardware: Provide classroom locks operable from inside with visual lock-status indicators, coordinated building keying, and two compatible Pro Lok Blue Punch keying machines or approved equivalents.
Door requirements: Meet scheduled fire ratings, accessibility, and egress requirements; include hardware adjustment and fire-door inspection and testing.
Site conditions: Buildings remain occupied. Include temporary dust, noise, and safety barriers, plus required asbestos/lead abatement, monitoring, and testing associated with the work.
Schedule: Complete within 365 days of order issuance. Weekday hours are 4 p.m.–midnight during the school year and 7:30 a.m.–4 p.m. during summer; work audible or visible within 300 feet is restricted to 7 a.m.–7 p.m.
Pricing: Provide a separate price for each location and a total.