How to Price a Government Contract Bid
Last updated:
Your price is often the part of a bid that decides the award. Price too high and you lose. Price too low and you either look like you misread the job or you win a contract that loses you money.
This chapter explains how agencies judge price, how to build your number from the bottom up, where the required wage rates come from, how to fill in the price schedule, and how to check your number against what the government has paid before.
How agencies judge price
Before you price, find the evaluation section of the solicitation (on many federal solicitations it is Section M, or the "basis for award" paragraph of a short RFQ). It tells you how much price matters.
Lowest price technically acceptable (LPTA)
The agency checks each offer against its minimum requirements on a pass/fail basis. Among the offers that pass, the lowest price wins. Extra features earn no credit. See FAR 15.101-2.
Best value tradeoff
The agency weighs price against factors like technical approach and past performance, and may award to a higher-priced offer if it is judged worth the difference. The solicitation states the factors and their relative importance. See FAR 15.101-1.
Simplified acquisition
Smaller purchases use the faster procedures in FAR Part 13. The RFQ says how quotes will be evaluated: sometimes price alone, sometimes price plus a few other factors. These are usually the best first targets for a small business.
Whatever the method, the contracting officer must find the price fair and reasonable. FAR 15.404-1 lists the usual checks: comparing offers against each other, against prior prices paid for similar work, and against the government's own estimate.
Building your number
Build the price from the bottom up, one cost at a time, for the full period of performance in the solicitation.
- Labor. Hours per task times the hourly rate for each worker. On covered contracts, the rate can be no lower than the attached wage determination, plus any required fringe benefits.
- Materials and supplies. Use real supplier quotes, not memory. Note how long the quote is valid.
- Equipment. Rental, fuel, wear, and anything you must buy for this job.
- Travel. Mileage, drive time, lodging, and parking or site access costs.
- Overhead. Insurance the contract requires, bonds, payroll taxes, office costs, and the time spent on reports and invoicing.
- Profit. Add it as a separate, deliberate line. FAR 15.404-4 recognizes profit as part of a fair price.
If the contract has option years, price each year. Labor and material costs rarely stay flat for five years. Our free subcontractor quote template lays these lines out for you.
Service Contract Act and Davis-Bacon wage determinations
Two federal labor laws set minimum pay on many contracts, and both use a published wage determination (WD) for the area and type of work.
- Service Contract Act (now called the Service Contract Labor Standards, 41 U.S.C. chapter 67) covers most federal service contracts over $2,500, such as janitorial, grounds and guard work. Its WDs list an hourly rate per occupation plus a health and welfare fringe amount. See FAR subpart 22.10.
- Davis-Bacon Act (40 U.S.C. 3141 and following) covers federal construction contracts over $2,000 and sets prevailing wages by craft and county. See FAR subpart 22.4.
The WD that applies is usually attached to the solicitation. You can also search WDs by state, county and type on SAM.gov: https://sam.gov/content/wage-determinations. The U.S. Department of Labor Wage and Hour Division explains the rules: https://www.dol.gov/agencies/whd/government-contracts.
Price every worker at or above the WD rate, including fringe. Many states and cities have their own prevailing wage laws for public work, so check the state or local solicitation too. Trade examples are in our janitorial and construction guides.
Firm-fixed-price vs time-and-materials vs unit pricing
The price schedule is a list of contract line items (CLINs), each with a description, quantity, unit and price. FAR subpart 4.10 sets how line items are numbered. Fill in every CLIN, for every year, in the format asked.
- Firm-fixed-price (FFP). One price for the defined work. If it costs you more, you absorb it (FAR 16.202). The most common type for small jobs.
- Time-and-materials (T&M). Fixed hourly labor rates that include overhead and profit, plus materials at cost. Agencies use it only when no other type is suitable (FAR 16.601).
- Unit pricing. A price per unit, such as per mow, per square foot or per service call, multiplied by an estimated quantity. Common on recurring service and construction bid schedules.
On unit-priced schedules, keep each line priced on its own costs. Loading one line high and another low to game the estimated quantities is unbalanced pricing, and FAR 15.404-1(g) lets the agency reject an offer for it.
Checking your price against past awards on USAspending.gov
Once you have a number, see what the government paid for similar work. On USAspending.gov, filter by awarding agency, NAICS code, product or service code and place of performance, then open individual awards.
Compare carefully. An award amount can cover several option years, a larger building, or more frequent service. Divide by years and scope before you judge. Use past awards as a sanity check, not as a number to copy.
Common pricing mistakes that disqualify a bid
- Blank or missing CLINs. A missing line, or a skipped option year, can make the offer incomplete.
- Paying below the wage determination. Your price must cover the required wages and fringe for the whole contract.
- Changing the schedule. Adding your own line items, units or conditions ("price valid 30 days") when the solicitation did not ask for them.
- Math errors. Unit price times quantity must equal the extended price, and the lines must add up to the total.
- Ignoring amendments. An amendment can change quantities or the WD. Acknowledge every one and reprice if needed.
- Pricing far below everyone else. It can raise doubt that you understood the work, and it can lock you into a loss.
- Unbalanced unit prices. See the CLIN section above.
More on reading the scope before pricing is in our HVAC contracts guide.
Price it once, let XL Eagle bid as prime
If registrations, forms and federal paperwork are what keep you from bidding, you can do just the pricing. XL Eagle finds open federal, state and local bids and bids as the prime contractor. You send us your price on an open bid, and if we win, you do the work as our subcontractor at your price.
There are no fees to bid, and we send nothing to the buyer without your OK. Find an open bid in your trade and send your price. To learn how the prime and subcontractor roles split, read subcontracting for government primes.
Frequently asked questions
Does the lowest price always win a government contract?
No. Under lowest price technically acceptable, the lowest price among offers that pass the technical review wins. Under a best value tradeoff, the agency may pay more for a stronger offer. The solicitation states which method applies.
Where do I find the wage rates I have to pay on a government contract?
Covered service and construction contracts include a wage determination, usually as an attachment. Wage determinations are also published on SAM.gov. The U.S. Department of Labor Wage and Hour Division administers them.
How do I know what similar contracts sold for?
Search USAspending.gov by agency, NAICS code, product or service code and place of performance to see past federal awards and their amounts. Read the scope and period of performance before comparing, because award totals can include option years.
Can a price be too low?
Yes. A price far below the others can make the contracting officer doubt you understood the work, and it can leave you losing money for the whole contract. Price the work you will actually perform, including required wages.
Can XL Eagle bid my price for me?
Yes. Send your price on an open bid. XL Eagle bids as the prime contractor and, if we win, you do the work as our subcontractor at your price. There are no fees to bid, and we send nothing to the buyer without your OK.
This guide is general information, not legal advice. Always follow the solicitation and the official sources: https://www.acquisition.gov/far/15.404-1, https://sam.gov/content/wage-determinations, https://www.dol.gov/agencies/whd/government-contracts, https://www.usaspending.gov