The original documents
Deadline: December 1, 2026
See the original on miamiu-ohiousourcing.ionwave.net
Bidding it yourself? Get the full package and submit on Ionwave before December 1, 2026.
What they need
- BatteriesReplace two approximately 125 VDC banks, each with 92 Hoppecke FNC 176L NiCad cells (184 total), including connectors, jumpers, hardware, and leads.
- Chargers and containmentSupply and install two HindlePower ATevo ATEV1130050F208SS1XB1 chargers and two Enviroguard Eagle Series spill containment systems sized to the racks.
- RackingProvide two-tier, two-step seismic racks; existing racks may be reused if compatible with the new cells.
- InstallationInclude all labor and materials, reuse existing wiring and charger power, and replace one bank at a time while maintaining control power. Skid removed batteries one layer high for university-arranged recycling.
- TestingPerform battery and charger acceptance testing to IEEE, NETA, and manufacturer requirements, including IEEE 1106-2015 capacity discharge testing. Include testing reports and operation and maintenance manuals.
- ScheduleOn-site work must start on or before January 4, 2027, with substantial completion by June 30, 2027.