Control booths: Build security booths/control stations in two Level IV housing units and renovate the segregation unit control booth.
Doors and hardware: Replace cell door operators, locks, tracks, guides, receivers, switches, and controls; reconnect existing control cabling.
Cell doors: Relocate, clean, modify, and install 202 sliding doors from Standish Correctional Facility; supply 12 new accessible cell doors. Include food-slot modifications, painting, and associated entrance/stairwell door work.
Phasing: Work in occupied housing units with temporary smoke-barrier partitions, handling four doors at a time in housing units and two at a time in segregation.
Pricing: Include separate deductions for omitting Building 1200 work and segregation unit work.