This bid is for generator transfer switch installations at two well houses: 460 W. Minnehaha Ave., Clermont, FL 34711, and 100 Bloxam Ave., Clermont, FL 34711.
Can you do this job? Tell us your price.
We write the bid, handle the paperwork, and submit it for you. No upfront fees.
Got it.
You send a priceOne number, before November 12, 2026.
We bid itXL Eagle submits the bid as the main contractor.
You do the workIf it is awarded, you do the job as our subcontractor.
Switches: Furnish and install one new 400-amp, 480-volt, three-phase, three-position Utility-Off-Generator switch at each site, with an outdoor-rated NEMA 3R enclosure.
Installation: Connect in-line with each existing 400-amp service, including new conductors from the existing disconnect to the switch and onward to existing load-side equipment, all terminations, conduit, fittings, supports, and hardware.
Included work: Provide labor, materials, equipment, permitting drawings, permits, inspections, coordinated shutdowns, testing in all three switch positions, and cleanup. Florida electrical contractor licensing is required.
Schedule and warranty: Substantial completion within 30 calendar days of authorization to proceed, with final completion within 15 days afterward. Include manufacturer warranties and a minimum one-year workmanship warranty.
Pricing: Provide a separate lump-sum price for each location and estimated transfer switch lead times.