This bid is for mechanical site preparation and fuels reduction at Cherry West, Groveland Ranger District, Stanislaus National Forest, Tuolumne County, California.
Can you do this job? Tell us your price.
We write the bid, handle the paperwork, and submit it for you. No upfront fees.
Got it.
You send a priceOne number, before November 13, 2026.
We bid itXL Eagle submits the bid as the main contractor.
You do the workIf it is awarded, you do the job as our subcontractor.
Scope: Approximately 535.90 acres across 13 units, including mastication, chipping, thinning, snag treatment, grapple piling and hand piling.
Terrain: Approximately 6,000 feet elevation with seasonal snow access limits. Hand cutting and piling required on 45–55% slopes and mechanically inaccessible areas.
Treatment: Thin conifers to prescribed spacing while retaining designated trees and riparian vegetation. Limit masticated debris to 3 feet long and 12 inches deep; chipped material to 6 inches deep.
Piles: Minimum machine piles 10 × 10 × 10 feet; hand piles 10 × 10 × 5 feet. Include waterproof covers, fuel breaks and fire lines.
Equipment: Include a tracked, boom-mounted masticator capable of treating 20-inch material and equipment capable of mulching material 6 inches into soil. Include required fire suppression equipment.
Schedule: Priority units M014A and M014C start no earlier than June 2027. Complete at least 50% of the acreage, including both priority units, by October 31, 2027; finish remaining work by October 31, 2028. Seasonal wildlife and fire restrictions apply.
Pricing: Provide per-acre and total pricing by unit, including labor, equipment, mobilization, road upkeep, dust control and erosion control. Prevailing wages and active DIR registration are required.