Structured Cabling Installation

This bid is for structured cabling installation at Heritage High School, 26001 Briggs Rd, Romoland, CA 92585; Paloma Valley High School, 31375 Bradley Rd, Menifee, CA 92584; and Perris High School, 175 E Nuevo Rd, Perris, CA 92571.

Due
January 7, 2027
40 days left
Location
Texas
Posted on
Bonfire
Notice ID
2026-2027/06

Please quote structured cabling installation at Heritage High School in Romoland, Paloma Valley High School in Menifee, and Perris High School in Perris, California.

  • Heritage: Install 308 Cat 6A drops across 15 IDF locations, 16 new 48-port patch panels, and 154 green 28AWG slim Cat 6A patch cables each at 7-inch and 9-inch lengths.
  • Paloma Valley: Install 4 Cat 6A and 17 Cat 6 drops on existing patch panels, move existing fiber and tray to a new four-post rack in the same room, and install 3 Leviton 5R4UH-S12 fiber trays or equivalents.
  • Perris: Install 28 Cat 6A drops, relocate 192 Cat 6 drops, consolidate fiber into one panel, provide 4 new 48-port patch panels, reuse 1 existing panel, and install a 48x24x30 inch wall-mount IDF cabinet in Room 6101.
  • Patch cables: Perris needs 28AWG slim cables: green Cat 6A, 14 each at 7-inch and 9-inch; blue Cat 6, 96 each at both lengths.
  • Installation: Wireless locations get two Cat 6A cables with green jacks in dual-port biscuit receptacles; outdoor terminations need weathertight boxes. Work includes pathways, supports, terminations, grounding, removing abandoned cabling, testing, labeling, as-built drawings, and cleanup.
  • Schedule: Work outside instructional hours and keep existing connections working until cutover.

Please confirm availability and send your quote by January 7, 2027.

The original documents

Deadline: January 7, 2027

See the original on kelloggllc.bonfirehub.com

Bidding it yourself? Get the full package and submit on Bonfire before January 7, 2027.

What they need

  • HeritageInstall 308 Cat 6A drops across 15 IDF locations and 16 new 48-port patch panels. Provide green 28AWG slim Cat 6A patch cables: 154 each at 7-inch and 9-inch lengths.
  • Paloma ValleyInstall 4 Cat 6A and 17 Cat 6 drops using existing patch panels. Relocate existing fiber and tray to a new four-post rack in the same room; assume sufficient fiber slack. Install 3 Leviton 5R4UH-S12 fiber trays or equivalents.
  • PerrisInstall 28 Cat 6A drops, relocate 192 Cat 6 drops, and relocate/consolidate existing fiber into one panel. Provide 4 new 48-port patch panels, reuse 1 existing panel, and install one 48-inch H × 24-inch W × 30-inch D wall-mount IDF cabinet in Room 6101. Provide 28AWG slim patch cables: green Cat 6A, 14 each at 7-inch and 9-inch lengths; blue Cat 6, 96 each at both lengths.
  • InstallationWireless locations require two Cat 6A cables with green jacks in dual-port biscuit receptacles; outdoor terminations require weathertight boxes. Include pathways, supports, terminations, grounding, abandoned cabling removal, testing, labeling, as-built drawings, and cleanup. Follow the site's cabling standards and schedule work outside instructional hours, keeping existing connections operational until cutover.
  • Site walkMandatory December 3, 2026, at 12:30 p.m. Pacific, starting at Perris High School.
  • PricingItemize materials and labor by site, including shipping, taxes, and all installation costs.