The original documents
Deadline: December 3, 2026
See the original on www.commbuys.com
Bidding it yourself? Get the full package and submit on COMMBUYS before December 3, 2026.
What they need
- Mainline liningEstimated CIPP quantities: 400 LF of 6-inch, 2,300 LF of 8-inch, 100 LF of 10-inch, and 1,200 LF of 12-inch sewer; include preparation, CCTV inspections, testing, and service reopening.
- Cleaning1,000 LF of heavy cleaning and 1,600 LF of chemical root treatment.
- Service connections13 liners extending at least 3 feet into laterals, 34 connections tested and sealed, 12 open-cut replacements with 6-inch PVC, and 9 protruding taps ground down.
- RepairsRebuild 9 manhole channels and shelves; replace up to 8 LF of 8-inch sewer with PVC at the Stevens Circle easement; allow 10 LF of additional main replacement and 5 CY of rock excavation.
- Separate optional pricingAdditional 1,500 LF of 6-inch and 700 LF of 8-inch CIPP, 13 service liners, 32 connections tested and sealed, and 17 tap grind-downs; separately price 100 vertical feet of cementitious manhole lining, 14 chimney repairs/liners, 8 channel/shelf rebuilds, 1 internal drop connection, and 3 frames and covers.
- ExecutionInclude bypass pumping, traffic management, restoration, and cleanup. Completion within 180 calendar days; weekday work between 7 a.m. and 5 p.m. Applicable prevailing wage rates apply.