This bid is for concrete, masonry, and steel repairs at Fire Station #3, 114 Hubbard Lane, Williamsburg, VA 23185.
This bid has closed.
Buyers often post the same work again. Set an alert below and we will email you when a similar Virginia bid is posted.
What the job is
Concrete: Remove and replace approximately 35 ft 7 in by 6 ft of entrance slab, 8 inches thick, using 4,000 PSI concrete with #5 reinforcing bars at 12 inches on center each way; include dowels, joints, and stainless steel angles at vehicle doors.
Steel jamb: Replace the deteriorated base with 12-gauge bent plate matching the existing profile, including welded connections, anchors, base weeps, zinc-rich primer, and high-performance coating.
Masonry and shoring: Remove and replace affected door-jamb CMU, grout solid, and shore the adjacent door header with post jacks before demolition; the masonry load above the header is 600 lbs.
Site protection: Keep the station functioning with safe access; provide security and weather protection outside working hours.
Pricing and schedule: Include labor, materials, equipment, permits, testing, and debris disposal in a lump-sum quote. Substantial completion is required within 60 calendar days of authorization to start, with final completion within 75 days.