This bid is for roadway and bridge construction on I-490 from Taft Avenue to Beeline Drive, mile posts 0.9–2.8, in DuPage and Cook Counties, Illinois.
This bid has closed.
Buyers often post the same work again. Set an alert below and we will email you when a similar Illinois bid is posted.
What the job is
Earthwork: Excavation, grading, stockpiles, and haul road construction and maintenance; includes 200,950 cubic yards of earth excavation.
Paving: Mainline and ramp pavement, subbase, shoulders, and removals; includes 59,885 square yards of 10-inch performance-related concrete pavement and 36,354 square yards of 10¼-inch jointed concrete pavement.
Structures: Bridges, structural steel, piling, and retaining walls, including 31,685 square feet of mechanically stabilized earth wall.
Site infrastructure: Drainage, erosion control, landscaping, fencing, lighting, traffic signals, ITS infrastructure, toll plaza facilities, and overhead sign foundations.
Site coordination: Maintain traffic and protect aviation equipment and existing utilities.
Schedule: Anticipated start March 22, 2027; completion by July 15, 2030.