The purpose of this amendment to the solicitation is to: Extend response due date to 8/26/2026 Respond to questions. First set of questions: 1. Project Sequencing RFI 1 - Hydrostatic Test Sequence The Statement of Work requires hydrostatic testing of Boiler No. 2; however, the required timing of the test is not clearly defined.
Establishing the condition of the boiler pressure boundary before burner work begins will reduce the risk of performing substantial work on a boiler that has not yet passed the required pressure test. Requested VA Response: Please confirm whether the hydrostatic test must be completed, witnessed, and accepted before burner replacement work or other irreversible modifications begin. If a different sequence is intended, please identify the required sequence. VA Response: The hydrostatic test must be completed, witnessed, and accepted before burner replacement work or other irreversible modifications begin.
2. Existing Safety and Equipment Conditions RFI 2 - Boiler No. 2 Main Steam Safety Valves The inspection information and field observations indicate that the two Boiler No. 2 main steam safety valves are leaking.
Existing valve data also indicates that the valves are not properly sized under the VHA Boiler and Associated Plant Safety Device Testing Manual, 8th Edition (BEI) capacity criteria and are iron-bodied. The BEI 8th Edition calls for approximately 80% of boiler steam capacity at the lower set pressure and at least 100% at the higher set pressure; the proposed replacement valves are to have carbon-steel bodies. Requested VA Response: Please confirm whether the base contract is to include removal and replacement of both Boiler No. 2 main steam safety valves with properly sized carbon-steel, ASME-stamped and National Board-certified valves, …
More like this: HVAC contracts in New York
XL Eagle · Certified Small Business · CAGE 11R42 · info@xleagle.com · (832) 380-5845